PROJECT PROGRESS
Please revisit to view monthly project progress.
PROJECT TIMELINE
Q1 - 2022 - Casting of 50 Tower Floors out of total of 147
Q3 - 2022 - Casting of 90 Tower Floors out of total of 147
Q1 - 2023 - Casting of 125 Tower Floors out of total of 147
Q3 - 2023 - Completion of Roof Concreting of all 05 Towers
Q1 - 2024 - Completion of installation of Fire Hydrant System
Q3 / Q4 - 2024 - Handing Over
OVERALL MILESTONES COMPLETED - 50%
Construction of the super structure of Marina Square - Uptown Colombo Project commenced on the 04th of November 2019, with the selection of China Harbour Engineering Company as the main contractor of the project.
The project is expected to be completed by 2nd quarter of 2024 and to start handing over the apartments to homeowners from the 3rd quarter of 2024 through to the 4th quarter of 2024.