项目进度
位于北科伦坡,一个快速发展的社区;紧邻中央商务区,一系列基础设施网络以及兴起的港口城市–科伦坡住宅区将成为该市增长最快的地区。
OVERALL MILESTONES COMPLETED - 70%
施工状态
Construction of the super structure of Marina Square - Uptown Colombo Project commenced on the 04th of November 2019, with the selection of China Harbour Engineering Company as the main contractor of the project.
总体施工状态
内部
100%
墙
100%
外观
100%
墙
100%
90 Floors
100%
125 Floors
100%
Roof Topoff
100%
Fire System
12%
Handing Over
0%
项目进度
Marina Square Site Progress
2024
November